What often results in project scope creep when functional requirements are not defined as well as they could be?
A . Inadequate software baselining
B . Insufficient strategic planning
C . Inaccurate resource allocation
D . Project delays
Answer: A
Explanation:
Inadequate software baselining often results in project scope creep because functional requirements are not defined as well as they could be.