Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Posted by: Pdfprep Category: PSM II Tags: , ,

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.
A . True
B . False

Answer: B

Explanation:

Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.