In the event of a conflict between the project specification and the coating manufactures’ product data sheet, the Inspector’s first course of action should be too:
A . Call the coating manufacturer for clarification
B . Use the product data sheet as a guide
C . Use the job specification as a guide
D . Call the person who wrote the specification for clarification
Answer: C