A material has been set up as a phantom assembly by entering the special procurement key in the material master .
How can you switch off the phantom assembly in a specific bill of material (BOM)?
A . Change the item category of the phantom assembly in the BO
C . Change the explosion type of the phantom assembly in the BO
E . Change the phantom item indicator for the phantom assembly in the BO
G . Change the special procurement key of the phantom assembly in the BO
Answer: B