Refer to Case 3.
You are tasked with designing a cloud. You review the existing infrastructure and business requirements. You select a Do-It-Yourself solution to expand the existing Platform 2.0 infrastructure. Before presenting this solution to the company, you must calculate the 3-year TCO using the following criteria:
• Hardware and software maintenance = $ 35,000
• Orchestration software licensing = $ 25,000
• Storage = $ 6,000 (6 TB @ $ 1/GB)
What is the correct TCO value?
A . $ 66,000
B . $116,000
C . $128,000
D . $198,000
Answer: D
Explanation:
TCO = 25.000 + (35.000 + 6.000 )