Posted by: Pdfprep
Post Date: April 2, 2021
A component project of a multiyear program delivers all expected products and services as anticipated . The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.
What should the program manager do next?
A . Reassign the component project manager to another component project or activity
B . Verify that the benefits were delivered and authorize component project closure
C . Conduct a program audit to confirm that the component project is complete
D . Keep the component project open until the program benefits are realized
Answer: B
Leave a Reply