A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building.
Which of the following correctly defines the organization in program management terminology?
A . Negative stakeholder
B . Positive stakeholder
C . Key stakeholder
D . Hurdle stakeholder
Answer: A