The program manager plans to address a negative cost variance generating a red flag in the program management status report.
What should the program manager do?
A . Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance.
B . Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction.
C . Work with program sponsor to compile impact analysis data to obtain additional funding for the program.
D . Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction.
Answer: B