A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product’s delivery time.
What should the program manager update first?
A . Procurement management plan
B . Benefits register
C . Risk register
D . Benefits management plan
Answer: B