A program with six projects has been running for three years . The company’s procurement and contracts department has compiled a qualified seller list . The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?
A . Plan a proposal evaluation system
B . Prepare the program procurement management plan
C . Perform the required program budget updates
D . Issue requests for proposals
Answer: D