A project is assigned to a qualified project manager by the program manager . The client rejects the project manager due to a lack of proper qualifications to manage such a project.
What should the program manager do next?
A . Reassess the project manager’s credentials
B . Assign a different project manager
C . Review the skill requirements of the project
D . Apply the competence assessment techniques to resolve the issue
Answer: D