Posted by: Pdfprep
Post Date: April 24, 2021
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
A . Project Management Information System
B . Integrated Change Control
C . Scope Verification
D . Configuration Management System
Answer: D
Leave a Reply